An application study of air conditioning and ventilation for the new offices of the factory was prepared.Then the installation of the system was carried out by our qualified crews, where the 1st installation of LG’s MULTI V5 in Attica with two 30HP outdoor units and 28 indoor units was carried out.

The completion time was ten days.

Location :Oinofyta Attica
Area :500.00τ.μ.
Year of Construction :2017
Interventions :Study & Construction
Duration of work : 10 days